Worker Accommodation on Construction Sites: A Planning Guide for Contractors

Published November 19, 2026 · 7 min read

On most construction and infrastructure projects, worker accommodation is planned late and built in a hurry. The camp then shapes daily productivity for the rest of the project: how long crews commute, how well they rest, and how many people the site can absorb when the schedule tightens. A few decisions made early avoid most of the problems that appear later.

Start from the peak headcount, not the average

Labor curves on a construction project rise, peak and fall. A camp sized to the average leaves the site short of beds exactly when the program needs the most hands. Size the camp to the peak, then decide whether the excess will be handled by phasing the build, by temporary overflow housing, or by relocating part of the camp to the next project once the peak has passed.

From the peak headcount, work out three numbers: occupants per room, which follows local labor regulations and the client's welfare standards; the number of rooms; and the shared facilities, including washrooms, canteen seating, laundry, a first-aid room and a site office. Shared facilities typically take a significant share of the camp footprint, and they are the buildings most often forgotten in early estimates.

Two-story worker accommodation blocks and a steel shed at a construction site in Thailand
Two-story worker accommodation blocks at a construction site in Thailand.

Choose the structure by site conditions

Most contractors now build worker camps from prefabricated container houses. The term covers several structures that perform differently in freight and installation, so the choice should follow the site, not the brochure. The figures below are for 20ft units, taken from the published specifications of one manufacturer's range.

StructureFloor areaUnits per 40HCInstallation per unitCrane needed
Detachable (bolted)about 18 m²18about 2 hours, 4 workersNo
Z foldingabout 14 m²10about 18 minutes, 4 workersYes
Flat pack (welded frames)about 14 m²8about 1 hour, 4 workersYes

For worker camps, the detachable structure is usually the default. It ships at the highest density, it needs no lifting equipment, and the same components form dormitories, washrooms, canteens and offices, which keeps the order and the spare parts simple. Folding units suit sites where a crane is on hand and speed per unit matters more than freight. Flat pack units suit long-term camps with heavier loads and higher wind exposure.

Workers bolting together a demountable container building on site
A detachable unit is bolted together by hand, without a crane.

Plan the freight before the floor plan

On overseas projects, sea freight and inland haulage often cost more than contractors expect. A 200-unit camp built from detachable units of the 20ft size ships in about 12 containers. The same camp in Z folding units needs 20, and in flat pack units 25. Ask every supplier for a loading plan with the quotation, and check the inland route for container weight and turning limits.

Knock down container house components packed in a shipping container
Detachable components packed for shipping.

Think about the next project now

A worker camp rarely has value once its project ends, unless it can move. Bolted structures can be dismantled and rebuilt; the Bolto detachable container house, for example, is rated for more than 50 cycles of dismantling and reassembly with a design service life of 10 years. For a contractor running several projects in one region, a camp that moves from site to site turns accommodation from a project cost into a reusable asset.

What this looks like in practice

Shinehive, a modular house manufacturer that supplies camps to EPC contractors and resource companies, publishes several worker accommodation projects built from detachable units. A 200-unit workforce camp in Thailand combined two-story dormitory blocks with a steel shed for shared facilities. At the smaller end, a 24-unit workers' camp in Indonesia used the same structure. Larger references include a 300-unit oil field camp in Angola delivered in 30 days.

Before requesting quotes: send every supplier the same brief, with peak headcount, occupants per room, the list of shared facilities, site location and nearest port, crane availability, and the date the first crew arrives. Comparable answers to the same brief are worth more than a comparison of unit prices.

A short checklist

  1. What is the peak headcount, and when does it occur?
  2. Which shared facilities are required by the client or local regulations?
  3. Is a crane available during camp installation?
  4. How many containers will the camp need, and can the inland route take them?
  5. Will the camp be relocated after this project, and how many times?

Contractors who settle these five points before the tender stage usually get a camp that is ready when the first crews arrive and still useful after the last ones leave.